Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:LR1 L239 P-1764-A
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
7roof tile (LIVINGSTON) #4576 FLAT11/18/096w12/30/0932.92%
8FRNT DR.11/18/097w01/06/1028.21%
9prefab wall mfg. PLAN-1764 A11/18/092w12/02/0998.75%
11Truss mfg.PLAN-1764 A11/18/092w12/02/0998.75%
12Windows mfg.TAN LOW E NO GRIDS11/18/09112h12/08/0970.54%
Task(s) Scheduled to Start in Between 12/02/09and03/30/10
31Backfill Plumbing12/02/094h12/02/090%
33Final Excavate & Prep for foundations12/02/092d12/04/090%
34INSTALL POST TENSION CABLES12/07/091d12/07/090%
351.4 Inspection on Footings12/08/091d12/08/090%
36Termite Pre-treat12/09/091.5h12/09/090%
37Pour concrete for foundations & slabs12/09/091d12/10/090%
38Strip foundation forms, GRADE & CURE12/10/091d12/11/090%
41Snap Lines stand walls12/11/092d12/15/090%
132Draw #1 - 20%12/14/090.5h12/14/090%
42Plumb in Line - 1st Floor12/15/091d12/16/090%
All TasksFinished DatePercent Completed
3696 W. 37TH PL SPEC12/01/0910.6%
  Sign contract11/18/09100%
  Color Chart Completed (Notice to Proceed)11/18/09100%
  Long Lead Items12/01/0912.58%
    power meter long lead11/25/09100%
    Temporary Power /BLUE STAKE11/23/09100%
    roof tile (LIVINGSTON) #4576 FLAT12/01/0932.92%
    FRNT DR.12/01/0928.21%
    prefab wall mfg. PLAN-1764 A12/01/0998.75%
    post tension notification PLAN-1764 A11/26/09100%
    Truss mfg.PLAN-1764 A12/01/0998.75%
    Windows mfg.TAN LOW E NO GRIDS12/01/0970.54%
    order appliances 0%
     Cabinet Long Lead & Construction0%
     1 marble countertop (mfg) long lead/ formica kit0%
    order granite slab0%
    order VANITY/shower Tile (see specs)0%
    order Floor Tile 0%
     order Carpet 0%
    Fencing long Lead0%
    Gate mfg. Long Lead0%
  Site Work plus12/01/0994.12%
    Secure Permits11/27/09100%
    Build up House Pad11/20/09100%
    compaction test11/20/09100%
    Set Forms11/23/09100%
    Rough-in underground plumbing, sewer & other11/25/09100%
    Install temporary power service11/24/09100%
    1.3 Inspect Plumbing Under/temp pwr12/01/09100%
    Backfill Plumbing0%
  Foundation0%
    Final Excavate & Prep for foundations0%
    INSTALL POST TENSION CABLES0%
    1.4 Inspection on Footings0%
    Termite Pre-treat0%
    Pour concrete for foundations & slabs0%
    Strip foundation forms, GRADE & CURE0%
    TENSION CABLES0%
  Framing0%
    Snap Lines stand walls0%
    Plumb in Line - 1st Floor0%
    roof framing (trusses & Sheeting)0%
    complete interior framing0%
    INSPECTION ROOF/SHEAR NAILING0%
    Install Windows0%
  Utility Rough-Ins0%
    HVAC Calcs & layout0%
    Rough-in HVAC0%
    Rough-in gas plumb0%
    Rough-in Plumbing0%
    Rough-in electrical0%
    Rough-in phone, cable0%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.0%
  Dry In0%
    Install felt, flashing,HOT MOP0%
    Load Roof Tile0%
  STUCCO &LATH0%
    Complete Lathing0%
    1.9.2 Inspect Drywall/lathing0%
  Interior Finishes0%
    Insulation0%
      Place wall insulation0%
      Place ceiling insulation0%
    Drywall0%
      Install drywall - 1st floor overhead0%
      1.9.2 Inspect Drywall/lathing0%
      Tape and float 1st floor drywall0%
      Texture - and clean up0%
    Trim Carpentry0%
      install front door0%
      DOORS,BASE,SHELVING0%
    Paint 0%
      Exterior Trim Paint0%
      prep &Paint0%
    Cabinets & woodwork0%
      Cabinet Bases 0%
      Cabinet Subtops & Scribe mold & uppers0%
      base in fil/front lock0%
    Countertops0%
      Templates for Stone Tops 0%
      Install Stone Countertop0%
      Install formica Countertops0%
      install marble top 0%
     Tile installation0%
      tile mstr vanity0%
      tile backsplash in kit0%
      floor tile install0%
      Other first floor tile/ mstr bath floor0%
      Grouting0%
      Fix Grout0%
  EXTERIOR FINISHES0%
    Complete brown coat0%
    Rough Grade0%
    install cultured stone0%
    Pour concrete driveway and sidewalks0%
    Color Coat exterior0%
    Install Roof Tile 0%
    Install garage door0%
    Install fence0%
    INSTALL GATE0%
    landscaping0%
  FINAL TRIMS0%
    Finish Electrical0%
      Complete 1st floor circuits to service panel0%
      Finalize Electrical0%
    Install Light Fixtures (In & Out)0%
    communications TRIM - phone, cable0%
    Finish HVAC0%
      Complete 1st floor - zone 1 HVAC0%
      start check hvac0%
    Final Trim0%
      locks,stops screens,etc.appliances,etc.0%
      deliver appliances0%
      Install Stove, Dishwaster, etc0%
    Finish Plumbing0%
      re Install bath Fixtures0%
    RO AND SOFTNER0%
     mirrors SHWR DOOR0%
    Carpet0%
      Carpet 1st floor0%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/19/0960.38%
    Set up Loan11/19/09100%
    Draw #1 - 20%0%
    Draw #2 - 25%0%
    Draw #3 - 25%0%
    Draw #4 - 20%0%
    Draw #5 - 10%0%
    Closing0%