| Project: | LR1 L239 P-1764-A |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 7 | roof tile (LIVINGSTON) #4576 FLAT | 11/18/09 | 6w | 12/30/09 | 32.92% |
| 8 | FRNT DR. | 11/18/09 | 7w | 01/06/10 | 28.21% |
| 9 | prefab wall mfg. PLAN-1764 A | 11/18/09 | 2w | 12/02/09 | 98.75% |
| 11 | Truss mfg.PLAN-1764 A | 11/18/09 | 2w | 12/02/09 | 98.75% |
| 12 | Windows mfg.TAN LOW E NO GRIDS | 11/18/09 | 112h | 12/08/09 | 70.54% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 03/30/10 | |
| 31 | Backfill Plumbing | 12/02/09 | 4h | 12/02/09 | 0% |
| 33 | Final Excavate & Prep for foundations | 12/02/09 | 2d | 12/04/09 | 0% |
| 34 | INSTALL POST TENSION CABLES | 12/07/09 | 1d | 12/07/09 | 0% |
| 35 | 1.4 Inspection on Footings | 12/08/09 | 1d | 12/08/09 | 0% |
| 36 | Termite Pre-treat | 12/09/09 | 1.5h | 12/09/09 | 0% |
| 37 | Pour concrete for foundations & slabs | 12/09/09 | 1d | 12/10/09 | 0% |
| 38 | Strip foundation forms, GRADE & CURE | 12/10/09 | 1d | 12/11/09 | 0% |
| 41 | Snap Lines stand walls | 12/11/09 | 2d | 12/15/09 | 0% |
| 132 | Draw #1 - 20% | 12/14/09 | 0.5h | 12/14/09 | 0% |
| 42 | Plumb in Line - 1st Floor | 12/15/09 | 1d | 12/16/09 | 0% |
|
| All Tasks | Finished Date | Percent Completed |
| 3696 W. 37TH PL SPEC | 12/01/09 | 10.6% |
| Sign contract | 11/18/09 | 100% |
| Color Chart Completed (Notice to Proceed) | 11/18/09 | 100% |
| Long Lead Items | 12/01/09 | 12.58% |
| power meter long lead | 11/25/09 | 100% |
| Temporary Power /BLUE STAKE | 11/23/09 | 100% |
| roof tile (LIVINGSTON) #4576 FLAT | 12/01/09 | 32.92% |
| FRNT DR. | 12/01/09 | 28.21% |
| prefab wall mfg. PLAN-1764 A | 12/01/09 | 98.75% |
| post tension notification PLAN-1764 A | 11/26/09 | 100% |
| Truss mfg.PLAN-1764 A | 12/01/09 | 98.75% |
| Windows mfg.TAN LOW E NO GRIDS | 12/01/09 | 70.54% |
| order appliances | | 0% |
| Cabinet Long Lead & Construction | | 0% |
| 1 marble countertop (mfg) long lead/ formica kit | | 0% |
| order granite slab | | 0% |
| order VANITY/shower Tile (see specs) | | 0% |
| order Floor Tile | | 0% |
| order Carpet | | 0% |
| Fencing long Lead | | 0% |
| Gate mfg. Long Lead | | 0% |
| Site Work plus | 12/01/09 | 94.12% |
| Secure Permits | 11/27/09 | 100% |
| Build up House Pad | 11/20/09 | 100% |
| compaction test | 11/20/09 | 100% |
| Set Forms | 11/23/09 | 100% |
| Rough-in underground plumbing, sewer & other | 11/25/09 | 100% |
| Install temporary power service | 11/24/09 | 100% |
| 1.3 Inspect Plumbing Under/temp pwr | 12/01/09 | 100% |
| Backfill Plumbing | | 0% |
| Foundation | | 0% |
| Final Excavate & Prep for foundations | | 0% |
| INSTALL POST TENSION CABLES | | 0% |
| 1.4 Inspection on Footings | | 0% |
| Termite Pre-treat | | 0% |
| Pour concrete for foundations & slabs | | 0% |
| Strip foundation forms, GRADE & CURE | | 0% |
| TENSION CABLES | | 0% |
| Framing | | 0% |
| Snap Lines stand walls | | 0% |
| Plumb in Line - 1st Floor | | 0% |
| roof framing (trusses & Sheeting) | | 0% |
| complete interior framing | | 0% |
| INSPECTION ROOF/SHEAR NAILING | | 0% |
| Install Windows | | 0% |
| Utility Rough-Ins | | 0% |
| HVAC Calcs & layout | | 0% |
| Rough-in HVAC | | 0% |
| Rough-in gas plumb | | 0% |
| Rough-in Plumbing | | 0% |
| Rough-in electrical | | 0% |
| Rough-in phone, cable | | 0% |
| 1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc. | | 0% |
| Dry In | | 0% |
| Install felt, flashing,HOT MOP | | 0% |
| Load Roof Tile | | 0% |
| STUCCO &LATH | | 0% |
| Complete Lathing | | 0% |
| 1.9.2 Inspect Drywall/lathing | | 0% |
| Interior Finishes | | 0% |
| Insulation | | 0% |
| Place wall insulation | | 0% |
| Place ceiling insulation | | 0% |
| Drywall | | 0% |
| Install drywall - 1st floor overhead | | 0% |
| 1.9.2 Inspect Drywall/lathing | | 0% |
| Tape and float 1st floor drywall | | 0% |
| Texture - and clean up | | 0% |
| Trim Carpentry | | 0% |
| install front door | | 0% |
| DOORS,BASE,SHELVING | | 0% |
| Paint | | 0% |
| Exterior Trim Paint | | 0% |
| prep &Paint | | 0% |
| Cabinets & woodwork | | 0% |
| Cabinet Bases | | 0% |
| Cabinet Subtops & Scribe mold & uppers | | 0% |
| base in fil/front lock | | 0% |
| Countertops | | 0% |
| Templates for Stone Tops | | 0% |
| Install Stone Countertop | | 0% |
| Install formica Countertops | | 0% |
| install marble top | | 0% |
| Tile installation | | 0% |
| tile mstr vanity | | 0% |
| tile backsplash in kit | | 0% |
| floor tile install | | 0% |
| Other first floor tile/ mstr bath floor | | 0% |
| Grouting | | 0% |
| Fix Grout | | 0% |
| EXTERIOR FINISHES | | 0% |
| Complete brown coat | | 0% |
| Rough Grade | | 0% |
| install cultured stone | | 0% |
| Pour concrete driveway and sidewalks | | 0% |
| Color Coat exterior | | 0% |
| Install Roof Tile | | 0% |
| Install garage door | | 0% |
| Install fence | | 0% |
| INSTALL GATE | | 0% |
| landscaping | | 0% |
| FINAL TRIMS | | 0% |
| Finish Electrical | | 0% |
| Complete 1st floor circuits to service panel | | 0% |
| Finalize Electrical | | 0% |
| Install Light Fixtures (In & Out) | | 0% |
| communications TRIM - phone, cable | | 0% |
| Finish HVAC | | 0% |
| Complete 1st floor - zone 1 HVAC | | 0% |
| start check hvac | | 0% |
| Final Trim | | 0% |
| locks,stops screens,etc.appliances,etc. | | 0% |
| deliver appliances | | 0% |
| Install Stove, Dishwaster, etc | | 0% |
| Finish Plumbing | | 0% |
| re Install bath Fixtures | | 0% |
| RO AND SOFTNER | | 0% |
| mirrors SHWR DOOR | | 0% |
| Carpet | | 0% |
| Carpet 1st floor | | 0% |
| 1.12 Complete final inspection for certificate of occupancy | | 0% |
| Final Acceptance | | 0% |
| Cleanup for occupancy | | 0% |
| TOUCH UP PAINT | | 0% |
| Perform final walk-through inspection | | 0% |
| Complete punch list items | | 0% |
| Loan & Draw Schedule | 11/19/09 | 60.38% |
| Set up Loan | 11/19/09 | 100% |
| Draw #1 - 20% | | 0% |
| Draw #2 - 25% | | 0% |
| Draw #3 - 25% | | 0% |
| Draw #4 - 20% | | 0% |
| Draw #5 - 10% | | 0% |
| Closing | | 0% |