Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:LQ2 L96 PLAN 2 3-car ?
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
16 order 3 showers tile 07/02/092w01/04/1050%
Task(s) Scheduled to Start in Between 12/02/09and03/15/10
All TasksFinished DatePercent Completed
4594 W IRMA ST SPEC PLAN 2 3 CAR09/29/0962.43%
  Sign contract03/27/09100%
  Color Chart Completed (Notice to Proceed)03/27/09100%
  Long Lead Items07/30/0962.22%
    new owner0%
     order roof tile (la quinta)03/27/09100%
    Exterior Door Long Lead Time05/15/09100%
    post tension notification PLAN 2 3 CAR04/10/09100%
    prefab walls PLAN 2 3 CAR04/17/09100%
    Truss Long Lead time PLAN 2 3 CAR04/17/09100%
     order Windows04/16/09100%
    CONCRETE TRIM LONG LEAD TIME04/17/09100%
    order appliances CUSTOM0%
     order Cabinets 07/30/09100%
    order 3 bathroom vanities tile0%
     order 3 showers tile 07/17/0950%
     order Floor Tile Long Lead time0%
    stone countertop (mfg) long lead0%
    Carpet Long Lead Time04/10/09100%
    Fencing long Lead07/21/09100%
    Gate mfg. Long Lead0%
  Site Work plus04/16/09100%
    Secure Permits04/07/09100%
    Water Meter Installed03/27/09100%
    Build up House Pad03/31/09100%
    Set Forms04/06/09100%
    Install temporary power service04/07/09100%
    Rough-in underground plumbing, sewer & other04/14/09100%
    1.3 Inspect Plumbing Under/temp pwr04/15/09100%
    Backfill Plumbing04/16/09100%
  Foundation05/01/09100%
    Underground Electrical / Islands04/17/09100%
    Final Excavate & Prep for foundations04/17/09100%
    post tension cables installed04/20/09100%
    1.4 Inspection on Footings04/21/09100%
    Termite Pre-treat04/21/09100%
    Pour concrete for foundation and garage04/22/09100%
    Strip forms& CURE foundation04/24/09100%
    tension cables05/01/09100%
  Framing05/28/09100%
    Snap Lines04/24/09100%
    Deliver wall panels/lumber04/24/09100%
    deliver trusses04/28/09100%
    Frame 1st floor walls04/27/09100%
    Install 1st floor trusses05/04/09100%
    Complete roof framing (trusses & Sheeting)05/14/09100%
    INSPECTION ROOF NAILING05/15/09100%
    rough clean up05/15/09100%
    complete interior framing05/21/09100%
    INSPECTION SHEAR NAILING05/22/09100%
    Install Fireplace 05/28/09100%
    Install Windows05/22/09100%
  Utility Rough-Ins06/15/09100%
    HVAC Calcs & layout05/26/09100%
    Rough-in HVAC05/28/09100%
    Rough-in gas plumb06/05/09100%
    Rough-in Plumbing06/05/09100%
    Rough-in electrical06/11/09100%
    Rough-in phone, cable06/12/09100%
    rough clean up06/15/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.06/16/09100%
  Dry In06/15/09100%
    Install felt, flashing,Hot mop 06/12/09100%
    Load Roof Tile06/15/09100%
  LATHING07/07/09100%
    Complete Lathing06/19/09100%
    1.9.2 Inspect Drywall/lathing07/07/09100%
  Interior Finishes09/28/0940.41%
    Insulation06/22/09100%
      Place wall insulation06/22/09100%
      Place ceiling insulation06/22/09100%
    Drywall07/10/09100%
      Install drywall 07/06/09100%
      1.9.2 Inspect Drywall/lathing07/06/09100%
      Tape and float drywall07/08/09100%
      Texture - 1st floor07/10/09100%
      Drywall Cleanup07/10/09100%
    Trim Carpentry09/25/09100%
      install front door Hang doors07/22/09100%
      Baseboards,CROWN, SHELVING09/25/09100%
    Paint 09/28/09100%
      Exterior Trim Paint07/14/09100%
      prep and Paint 09/28/09100%
    Cabinets & woodwork0%
      Cabinet Bases 0%
      Cabinet Subtops & Scribe mold & uppers0%
      TEMPLATE FOR STONE0%
      INSTALL STONE TOPS0%
     Tile installation0%
      mud tops and shower0%
      snail shower0%
      walk in shower0%
      drop in tub deck0%
      tile mstr vanity0%
      tile 2nd vanity0%
      tile3rd vanity0%
      Fireplace Facing 10%
      Standard (Tile entry, kitchen, utility room and baths)0%
      Other first floor tile (bath floors)0%
      Grouting0%
      Fix Grout0%
  Exterior Finishes08/10/0921.79%
    Complete brown coat07/13/09100%
    Rough Grade07/24/09100%
    Pour concrete driveway and sidewalks0%
    INSTALL CONCRETE TRIM08/10/09100%
    Install COURTYARD fence0%
    Install garage door0%
    Color Coat exterior LA QUINTA0%
    Install Roof Tile0%
    Install Gate0%
    landscaping0%
  final trims0%
    Finish Electrical0%
      Complete 1st floor circuits to service panel0%
      Finalize Electrical0%
    Install Light Fixtures (In & Out)0%
    Complete communications wiring - phone, cable, computer, alarm0%
    Finish HVAC0%
      Complete 1st floor - zone 1 HVAC0%
      start check hvac0%
    Final Trim0%
      locks,stops screens,etc.appliances,etc.0%
      deliver appliances0%
      Install Stove, Dishwaster, etc0%
    Finish Plumbing0%
      Install all Plumbing Fixtures0%
    Shower doors and mirrors0%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    touch up paint and grout touch up0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule09/29/0926.09%
    Set up Loan03/27/09100%
    Draw #1 - 20%04/21/09100%
    Draw #2 - 25%05/15/09100%
    Draw #3 - 25%06/17/09100%
    Draw #4 - 20%09/29/09100%
    Draw #5 - 10%0%
    Closing0%