| Project: | SM1 L17 P-1500 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 12 | order appliances std bisque | 11/30/09 | 2w | 12/11/09 | 30% |
| 14 | 1 marble countertop (mfg) 1 wilsonart 4551-01 blackstar granite | 11/20/09 | 2w | 12/03/09 | 90% |
| 91 | Standard (Tile entry, kitchen, utility room and baths) | 12/01/09 | 4.5d | 12/07/09 | 44.44% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 01/11/10 | |
| 89 | install marble top and formica | 12/04/09 | 3h | 12/04/09 | 0% |
| 92 | Other first floor tile (bath floors) | 12/07/09 | 3.5d | 12/10/09 | 0% |
| 99 | Color Coat exterior x-580 sierra tan | 12/07/09 | 16h | 12/08/09 | 0% |
| 100 | Install Roof Tile | 12/09/09 | 2d | 12/10/09 | 0% |
| 101 | Install 2 garage doors taupe 1 opener | 12/09/09 | 1d | 12/09/09 | 0% |
| 102 | Install fence | 12/09/09 | 32h | 12/14/09 | 0% |
| 112 | Complete 1st floor - zone 1 HVAC | 12/09/09 | 8h | 12/09/09 | 0% |
| 93 | Grouting | 12/11/09 | 8h | 12/11/09 | 0% |
| 109 | Install Light Fixtures (In & Out) | 12/11/09 | 3d | 12/16/09 | 0% |
| 108 | Finalize Electrical | 12/14/09 | 8h | 12/15/09 | 0% |
| 116 | deliver appliances | 12/14/09 | 3h | 12/14/09 | 0% |
| 117 | Install Stove, Dishwaster, etc | 12/14/09 | 4h | 12/15/09 | 0% |
| 20 | Gate mfg. Long Lead | 12/15/09 | 16h | 12/16/09 | 0% |
| 110 | communications TRIM - phone, cable | 12/15/09 | 8h | 12/16/09 | 0% |
| 119 | Install all Plumbing Fixtures | 12/15/09 | 8h | 12/16/09 | 0% |