| Project: | LR1 L27 P-3037 C |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 13 | order appliances CUSTOM | 10/08/09 | 2w | 12/07/09 | 72.25% |
| 15 | 1 marble countertop (mfg) long lead/ formica kit | 11/25/09 | 2w | 12/09/09 | 52.25% |
| 19 | order Carpet | 11/30/09 | 1w | 12/04/09 | 60% |
| 80 | Templates for Stone Tops | 11/25/09 | 1.5w | 12/07/09 | 69.67% |
| 96 | Install Roof Tile | 11/20/09 | 10d | 12/03/09 | 90% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/18/09 | |
| 81 | Install GRANITE BATH AND KIT JUPARANA ST CECEILIA | 12/07/09 | 8h | 12/08/09 | 0% |
| 100 | landscaping | 12/07/09 | 5d | 12/16/09 | 0% |
| 115 | Install bath Fixtures | 12/07/09 | 1d | 12/07/09 | 0% |
| 119 | Carpet 1st floor | 12/07/09 | 8h | 12/07/09 | 0% |
| 89 | Grouting | 12/08/09 | 8h | 12/09/09 | 0% |
| 90 | Fix Grout | 12/08/09 | 1h | 12/08/09 | 0% |
| 111 | locks,stops screens,etc.appliances,etc. | 12/08/09 | 6h | 12/08/09 | 0% |
| 116 | RO AND SOFTNER | 12/08/09 | 1d | 12/08/09 | 0% |
| 120 | 1.12 Complete final inspection for certificate of occupancy | 12/08/09 | 1d | 12/09/09 | 0% |
| 82 | Install formica Countertops | 12/09/09 | 8h | 12/10/09 | 0% |
| 83 | install marble top | 12/09/09 | 3h | 12/10/09 | 0% |
| 117 | mirrors CHM OBS SHWR DOOR | 12/09/09 | 3d | 12/14/09 | 0% |
| 132 | Draw #5 - 10% | 12/09/09 | 0.5h | 12/09/09 | 0% |
| 21 | Gate mfg. Long Lead | 12/14/09 | 16h | 12/16/09 | 0% |
| 122 | Cleanup for occupancy | 12/14/09 | 8h | 12/15/09 | 0% |
| 123 | TOUCH UP PAINT | 12/15/09 | 1d | 12/16/09 | 0% |
|