Home > Customer Progress > Uncompleted Projects > Last Updated: 12/02/09

Project:LR1 L128 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
18order Floor Tile 09/30/090w10/13/090%
101landscaping11/18/095d12/10/0920%
Task(s) Scheduled to Start in Between 12/02/09and12/15/09
119Carpet 1st floor12/04/098h12/04/090%
122Cleanup for occupancy12/04/098h12/04/090%
112locks,stops screens,etc.appliances,etc.12/07/096h12/07/090%
123TOUCH UP PAINT12/07/094d12/10/090%
21Gate mfg. Long Lead12/09/0916h12/10/090%
124Perform final walk-through inspection12/11/091d12/11/090%
125Complete punch list items12/14/091h12/14/090%
133owner for closing12/14/091d12/15/090%