Home > Customer Progress > Uncompleted Projects > Last Updated: 12/02/09

Project:CS1 L8 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
107Shower doors and mirrors12/01/093d12/03/0966.67%
Task(s) Scheduled to Start in Between 12/02/09and12/08/09
91landscaping12/03/093d12/08/090%
1101.12 Complete final inspection for certificate of occupancy12/03/091d12/03/090%
112Cleanup for occupancy12/04/0916h12/07/090%
122Draw #5 - 10%12/04/090.5h12/04/090%
113TOUCH UP PAINT12/08/091h12/08/090%
114Perform final walk-through inspection12/08/091h12/08/090%
115Complete punch list items12/08/091h12/08/090%
123Closing12/08/091h12/08/090%