Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project ListRun Date & Time:12/02/09 4:29 pm
Project:LR L 197 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
115Complete punch list items11/09/090h11/09/090%
Task(s) Scheduled to Start in Between 12/02/09and11/27/09
All TasksFinished DatePercent Completed
3693 W 36TH PL DOMINGUEZ11/27/09100%
  Color Chart Completed (Notice to Proceed)09/03/09100%
  Long Lead Items10/29/09100%
    water meter long lead09/08/09100%
    Temporary Power /BLUE STAKE09/08/09100%
    roof tile/SHINGLE production # 160909/24/09100%
    Exterior Door mfg.09/10/09100%
    FRAMING NOTIFICATION PLAN 1609 w/ patio09/17/09100%
    Truss mfg. PLAN 1609w/ porch and patio09/17/09100%
    Windows mfg.09/03/09100%
    order appliances 10/23/09100%
     cabinet Long Lead10/16/09100%
     VANITIY countertop (mfg) long lead10/22/09100%
    order Floor Tile 10/20/09100%
    order formicaCOUNTERTOPS10/15/09100%
     order Carpet10/29/09100%
    Fencing long Lead10/27/09100%
    Gate mfg. Long Lead10/22/09100%
  Site Work plus09/11/09100%
    Secure Permits09/07/09100%
    Build up House Pad09/11/09100%
    call BLUE STAKE09/03/09100%
    Set Forms09/04/09100%
    Rough-in underground plumbing, sewer & other09/07/09100%
    Install temporary power service09/09/09100%
    1.3 Inspect Plumbing Under/temp pwr09/10/09100%
    Backfill Plumbing09/10/09100%
  Foundation09/17/09100%
    Final Excavate & Prep for foundations09/11/09100%
    INSTALL POST TENSION CABLES09/11/09100%
    1.4 Inspection on Footings09/14/09100%
    Termite Pre-treat09/15/09100%
    Pour concrete for foundations & slabs09/16/09100%
    Strip foundation forms, GRADE & CURE09/16/09100%
    GRADE & Cure foundation09/17/09100%
  Framing09/24/09100%
    Deliver LUMBER and trusses09/17/09100%
    Snap Lines stand walls09/18/09100%
    Complete roof framing (trusses & Sheeting)09/22/09100%
    INSPECTION ROOF NAILING09/23/09100%
    complete interior framing09/23/09100%
    INSPECTION SHEAR NAILING09/24/09100%
    rough clean up09/24/09100%
    Install Windows09/24/09100%
  Utility Rough-Ins09/25/09100%
    HVAC Calcs & layout09/21/09100%
    Rough-in HVAC09/22/09100%
    Rough-in Plumbing09/24/09100%
    Rough-in electrical09/25/09100%
    Rough-in phone, cable09/24/09100%
    rough clean up09/25/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.09/29/09100%
  Dry In09/29/09100%
    Install felt, flashing,HOT MOP09/25/09100%
    Load Roof Tile09/29/09100%
  STUCCO &LATH10/05/09100%
    Complete Lathing09/28/09100%
    1.9.2 Inspect Drywall/lathing10/05/09100%
  Interior Finishes10/30/09100%
    Insulation10/01/09100%
      Place wall insulation10/01/09100%
      Place ceiling insulation10/01/09100%
    Drywall10/09/09100%
      Install drywall - 1st floor overhead10/02/09100%
      1.9.2 Inspect Drywall/lathing10/05/09100%
      Tape and float 1st floor drywall10/08/09100%
      Texture AND CLEAN UP10/09/09100%
    Trim Carpentry10/13/09100%
      install front door10/12/09100%
      DOORS,BASE,SHELVING10/13/09100%
    Paint 10/14/09100%
      Exterior Trim Paint10/14/09100%
      prep &Paint10/14/09100%
    Cabinets & woodwork10/22/09100%
      Cabinet Bases 10/20/09100%
      Cabinet Scribe mold & uppers10/21/09100%
      base in fil & front door lock10/22/09100%
    Countertops10/30/09100%
      template formica10/22/09100%
      Install formica Countertops10/30/09100%
     Tile installation10/23/09100%
      Standard tile EXCEPT BEDROOMS10/23/09100%
  EXTERIOR FINISHES11/04/09100%
    Complete brown coat10/05/09100%
    Rough Grade10/06/09100%
    Pour concrete driveway and sidewalks10/08/09100%
    Color Coat exterior10/22/09100%
    Install garage door sandstone10/22/09100%
    Install fence10/20/09100%
    Install Gate10/21/09100%
    landscaping11/04/09100%
  FINAL TRIMS11/03/09100%
    Finish Electrical11/02/09100%
      Complete 1st floor circuits to service panel10/26/09100%
      Finalize Electrical11/02/09100%
    Install Light Fixtures (In & Out)10/29/09100%
    communications TRIM - phone, cable10/28/09100%
    Finish HVAC11/02/09100%
      Complete 1st floor - zone 1 HVAC10/27/09100%
      start check hvac11/02/09100%
    Final Trim11/02/09100%
      locks,stops screens,etc.appliances,etc.10/30/09100%
      deliver appliances10/26/09100%
      Install Stove, Dishwaster, etc11/02/09100%
    Finish Plumbing10/30/09100%
      Install all Plumbing Fixtures10/30/09100%
    Shower doors and mirrors11/03/09100%
    Carpet10/29/09100%
      Carpet 1st floor10/29/09100%
  1.12 Complete final inspection for certificate of occupancy11/03/09100%
  Final Acceptance11/09/09100%
    Cleanup for occupancy11/05/09100%
    TOUCH UP PAINT11/06/09100%
    Perform final walk-through inspection11/09/09100%
    Complete punch list items11/09/090%
  Loan & Draw Schedule11/27/09100%
    Set up Loan09/08/09100%
    Draw #1 - 20%09/15/09100%
    Draw #2 - 25%09/22/09100%
    Draw #3 - 25%09/30/09100%
    Draw #4 - 20%10/14/09100%
    Draw #5 - 10%11/04/09100%
    Closing11/27/09100%